Winter 2015

Tulare County Office of Education – Visalia, California

BUSH Construction has been busy erecting the steel structural frame on this nearly 95,000 sf three story building, to house three floors of office and support space, along with a fully flexible conferencing center and service kitchen – designed by Mangini Associates / Tellian Parish McLain Architects.


Hoover High School Aquatic Center – Fresno Unified School District

BUSH Construction started work on this all new aquatic center just before Christmas and is well on its way to completion of the pool itself with its ADA compliant access down into the water including a deep end to accommodate three diving boards. The support facilities are following along nicely – making ready for late spring swimming – designed by HMC Architects.


Coalinga High School Multi-Use / Classroom Facility

Roof-framing is well underway on this 20,000 sf all new structure - to house PE and Exercise Classrooms and other typical classroom spaces – designed by Mangini Associates / Tellian Parish McLain Architects.


Coalinga High School North Wing Modernization

BUSH is nearing completion on this 31,000 sf historical shops building on the high school campus – featuring architectural and structural restoration of this unique saw-toothed clerestory roof-framing and natural lighting system throughout – designed by Mangini Associates / Tellian Parish McLain Architects.


Clark Intermediate School – Clovis Unified School District

BUSH Construction has been focusing recently on the new 20,000 sf Admin/Classrooms Building on this multi-phased middle school project. The structural steel frame for this two story building is up, with light-gauge framing and scaffolding for exterior surfaces in progress – designed by Darden Architects.


Liberty Elementary School Multi-Purpose Bldg. – Kerman Unified School District

BUSH Construction is planning an early summer start on this nearly 10,000 sf concrete block multi-purpose building to house additionally a stage and serving kitchen – designed by TETER A/E.


Pixley Middle School Gymnasium – Pixley Union School District

BUSH Construction is planning a late-Spring start on this nearly 18,000 sf new Gymnasium/Bandroom building addition to the existing campus.